Hey contractors: Are your invoices for construction services and/or materials supplied to an improvement “proper”? Lessons learned from Arcamm v. Avision
Contractors[1] supplying construction services and/or materials to an improvement must render “proper invoices”[2] in order to rely on and take advantage of Part I.1 of Ontario’s Construction Act (the “Act”)[3] (hereinafter referred to as, the “Prompt Payment” regime). A “proper […]
The Divisional Court considers when a subcontractor’s lien rights expire where they have more than one subcontract
Introduction In Prasher Steel Ltd. v. Pre-Eng Contracting Ltd.,[1] the Divisional Court addressed a number of issues arising on appeal, including the differences between “contracts” and “subcontracts,” as those terms are defined by the Construction Lien Act, RSO 1990, c. […]